Friday, 15 December 2023 15:49

Friday, Dec. 15/23 BIA Update

Good Morning All,

A few construction updates for you all to be aware of as follows:
 
Broadview North:
  • Toronto Water will begin the sewer rehabilitation work starting this Sunday, Dec. 17 and through next week. This is prep work and will not affect water usage.  The work will take place from Sunday to next Thursday from 7pm to 7am.
  • During the above sewer prep work there will be parking restrictions on both sides of Broadview in this section.
  • Work in the streetcar loop continues and the east sidewalk of Broadview from Danforth to Erindale is still closed - barrels have been brought in to protect pedestrians who are walking on the road in that section.
  • Erindale from Ellerbeck to Broadview is still closed.
  • The # 8, 62, and 504/505 buses continue to stop in front of the station - at the Broadview/Danforth intersection. The #87 and 100 buses continue to divert to Pape Station until further notice.
Back Lane behind businesses on Danforth from Ellerbeck to Broadview;
  • Due to the extensive delays with the Broadview north construction it's been decided to delay redoing this back lane until early Spring 2024.  I will provide further updates in the new year.
60 Bowden Construction - Danforth & Bowden:
  • The new build construction on the south/west corner of Danforth and Bowden is now scheduled to start in the spring of 2024.  I will provide further updates in the new year.
Hope you all have a good weekend!
 
Susan
Read 611 times

RSS Twitter Facebook Instagram

Member Resources

Find a great list of reference and resource items for your business here and here.

54 Police Division: 416-808-5400
55 Police Division: 416-808-5500

Recent Tweets